PROJECT AUTHORIZATION PACKET ID: N/A
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
      69343 18
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER
017 0641 SPP
028 0641 SPP


01-00187 1-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
RELOCATE W/ADD LNS 14.7 MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
DOH/CONTRACT DOH
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL STATE DOH LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
1-187.2 C 1300 JL03 2017 $800,000.00
CURRENT FUNDING REQUEST TOTAL: $800,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $6,575,000.00
UTILITIES $3,750,000.00
R/W $3,475,000.00
CONSTRUCTION $39,797,885.00
NON-HIGHWAYS $0.00
  Total: $53,597,885.00
REMARKS: THIS MOD. PROVIDES ADDITIONAL CONSTRUCTION FUNDS TO COVER CHANGE ORDER #2 ($1,378,470.53)
 
Project Approval Recommended By:
JAB   11/3/2016
Signed and Approved by:
BW   11/4/2016
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
01-00187.20 CALDWELL
CRITTENDEN

1 US-62,US 641 US 641 14.7 MI RELOCATION OF US-641 FROM MARION TO FREDONIA (GRADE AND DRAIN)